Sunday, February 26, 2012

Update on Moseley Road baths – 26th February 2012

Work on the final phase to get Moseley Road baths re-opened in April is well under way.

Followers of the present saga to get these historic baths re-opened will be aware of how much hair I’ve been pulling out over this issue. What started out as a six week closure in December 2010 for a simple lintel replacement, escalated as health and safety found more and more issues to prevent its re-opening.

Each issue has been resolved and we are now on the final piece of work to remove all the flaky paint from the ceiling of Pool 2 and to replace all the stolen roof lead.

For more on the flaky paint issue, please read my blog report at http://martinmullaney.blogspot.com/2012/02/moseley-road-baths-re-opening-delayed.html

For more information on the stolen roof lead, please see my other blog report at http://martinmullaney.blogspot.com/2011/11/update-on-moseley-road-baths-19th.html

As you will see from the attached photos of the interior of Pool 2, the erection of the scaffolding is nearly complete. The scaffolding will be complete on Wednesday 29th February – one and a half weeks ahead of schedule.

Removal of the flaky paint using a special epoxy resin will begin straight away. A specially developed Dulux paint for use in a high humidity atmosphere will be applied. Flaky paint removal and repainting will take three weeks.

Removal of the scaffolding will then take 10 days.

Replacement of all stolen lead with a lead substitute will take place in parallel. Also, using the knowledge of the pools staff, efforts will be made to get rid of other roof leaks.

We estimate that all work will be complete by 4th April. The pools re-opening will then be based on how long it takes to refill the pool.

In the meantime, I’m hoping to have the report signed off to release the money to fund a heritage specialist to pull together the Heritage Lottery Bid for phase one of the works to restore the baths.

The total cost of phase 1 of the restoration works is £8million. Finance have agreed to set aside £3million in future capital budgets as the Council’s contribution to this restoration. This means we would apply for £4.99million from the Heritage Lottery Fund. With the bid under £5million, it will be considered by the Regional HLF Board. We have a far greater chance of a successful bid at regional level. If the bid was for £5million or more, than it would be considered at the national HLF board, where you are up against the Buckingham Palaces and Stonehenges of the World..

The submission of the HLF bid will now most likely go to Cabinet for approval in June. Any successful HLF has to go through two stages in the HLF process. If our bid was successful, then the earliest the HLF monies would be available is 2014.

The phase 1 restoration of Moseley Road baths will require the building to be closed to the public for two years and would do the following:

  • Permanent repairs to the exterior fabric of the building with a life of 25 years – so basically a complete re-roofing to stop any water ingress
  • Complete re-wiring and new machinery (eg new boilers) for the pool. We would be particular keen to install a combined heat and power system in the boiler house. This would heat all the buildings along Moseley Road and help to regenerate this corridor.
  • Pool 2 maintained as a community swimming pool
  • Pool 1 boarded over and used for community use.

Phase 2 of the restoration would involve getting pool 1 back in use as a swimming pool. Estimated cost of doing this is £9million.

The timing of 2014 as the earliest date for the start of phase 1 of the restoration fits in perfectly with the re-opening of Sparkhill pool in 2014. Once this re-opens, this will allow us to close Moseley Road baths for 2 years for this phase 1 restoration



moseley-road-bath1

moseley-road-bath2

0 Comments:

Post a Comment

<< Home